Basement Project: Day 8



 Behold!!!11
 Finished the Stud work !!! yesssss!!!!

  Future bar area/pantry setup, also hides the water main.


 Now thats a nice wall, went up in no time too.. 
 Now I get to start wiring it up, we will be adding a sub panel and a few extra circuits for the lights, office area, and outlets. 14/3 for the dual switched outlets, 14/2 for everything else, cat6 I think I will be running vertically to try and limit EMI interference...
Sump pump hiding spot/ AV reciever/xbox/dvd/htpc/etc hideout. :D



Feels good to be done with all that stud work, now its time for the fun stuff!